Boost to Infrastructure in South Western Railway
Budget Grant of SWR recorded 17% Growth for the year 2019-20 compared to that of 2018-19. Total Capital Outlay Rs.3516 Cr
1)Some of the important Plan Heads that recorded substantial increase of Budget grant over the last financial year are as under
Budgetary Grant 2018-19 Vs 2019-20(Figs in Cr. of Rs)
|
Plan Head
|
BG
2018-19 |
BG
2019-20 |
% increase
|
|
|
11.
|
New Lines
|
189
|
259
|
37
|
|
15.
|
Doubling
|
104
|
115
|
10
|
|
21.
|
Rolling stock
|
15
|
38
|
149
|
|
41.
|
Machinery &Plant
|
19
|
25
|
35
|
|
42.
|
Workshop & Prod Units
|
30
|
49
|
62
|
|
53.
|
Passenger Amenities
|
116
|
186
|
60
|
|
64.
|
Other Specified works
|
5
|
45
|
806
|
|
Total
|
1683
|
1927
|
14
|
|
|
EBR (IF)
|
731
|
548
|
-25
|
|
|
EBR (P)/Dep
|
576
|
1042
|
81
|
|
|
Grand Total
|
2990
|
3516
|
18
|
|
2)The Budget Grant for the year 2019-20 for Some
important works are as under
|
Sl.No
|
Plan Head
|
Section
|
BG
( In Rs. Cr) |
|
1.
|
New Lines
|
Rayadurg - Tumkur via
Kalyandurg
|
155
|
|
Bagalkot-Kudachi
|
20
|
||
|
Tumkur-Chitradurg-Davangere
|
115
|
||
|
Gadag -
Wadi
|
150
|
||
|
2.
|
Doubling
|
Yeshvanthpur-Channasandra
|
44
|
|
Baiyyappanahalli-Hosur
|
82
|
||
|
Hospet-Hubli-Londa-Tinaighat-Vasco
da Gama
|
259
|
||
|
Hotgi-Kudgi-Gadag
|
200
|
||
|
Yalahanka-Penukonda
|
132
|
||
|
Hubli - Chikjajur
|
102
|
||
|
Arsikere - Tumkur
|
103
|
||
|
3.
|
Quadrupling
|
Bangalore-Whitefield-Bangalore
City-Krishnarajapuram
|
50
|
3)Important New Works Sanctioned are as
under:
|
Sl. No
|
Plan Head
|
WORKS
|
Cost
( In Rs. Cr) |
|
1.
|
New
lines
|
Shimoga-Shikaripura-Ranebennur
|
965
|
|
Mysuru (Belagola) - Kushalnagar
|
1855
|
||
|
Hassan (Alur) - Belur
|
463
|
||
|
2.
|
New Works
|
Crossing stations, yard
remodelling, provision for addl running line
|
55
|
|
New Traffic Facility lumpsum
works
|
4
|
||
|
Interlocking & power supply
provision on interlocked level crossing gates
|
32
|
||
|
3.
|
ROB/RUB
|
Construction of Road Over/ Under bridges
(22 ROB & 16 RUB/Subway)
List
enclosed as Annexure
|
486
|
|
4.
|
Complete Track Renewal
|
Complete
Track Renewal
|
508
|
|
Primary track renewal namely
through rail
renewal,
through sleeper renewal, increasing sleeper density andthrough bridge timber
renewal
|
24
|
||
|
Secondary track renewal namely
complete
track
renewal, through rail renewal and through sleeper renewal
|
70
|
||
|
Through fastening renewal,
through ballast
renewal,
through formation treatment and through weld renewal etc
|
129
|
||
|
Through turnout renewal,
renewal of switch
expansion
joints, glued joints etc
|
44
|
||
|
Repl of
girders/slabs, rehabilitation/ strengthening of sub-structure & super
structure, rebuilding of bridges, bridge protection works,
|
50
|
||
|
Reliability
improvement, selective repl of signalling items and safety enhancement
through signalling system
|
10
|
||
|
5.
|
Coaching Depot
|
Development
of coaching depot at Koteganguru/ Talaguppa
|
62
|
4)Sanctioned Works in Plan Head – 53
Passenger Amenities under “Umbrella Works”
|
Sl. No.
|
Name of Work
|
Cost
(in Rs.Cr.)
|
|
1.
|
Foot Over Bridge and High Level Platform will be developed at
the following Stations.
|
85 Cr.
|
|
2.
|
Redevelopment of
Stations at Dharwar, Yeshwantpur, Mysuru &Hosapete
|
50 Cr.
|
|
3.
|
Provision of
Toilets, CC Aprons (Shivamogga Town, Davangere& Mysuru),
Cover Over
Platforms, Lifts
(Bangalore cantt,
Srisatyasaiprashanthinilayam, Yelhanka, Tumakuru, Gadag, Koppal, Arsikere,
Shivamogga Town & Hassan) & Other Misc. Works.
|
50 Cr.
|
Details of FOB and High level Platforms
|
Foot Over Bridge
(49 Nos. Stations)
|
High Level Platform
(81 Nos. Stations)
|
||
|
Division
|
Number and Name of Stations
|
Division
|
Number and Name of Stations
|
|
Hubballi
|
16
Stations
Gadiganuru,
Kudatini, Bhanapur, Toranagallu, Bannikoppa, Koppal, Haralapur, Sompur Road,
Gulegudda Road, Kambarganvi, Dharwar, Sisivanahalli, Ballari Cantt, Ballari,
Daroji&Londa
|
Hubballi
|
03
Stations
Daroji,
Munirabad, Ballari Cantt.
|
|
Bengaluru
|
20 Stations
Karuvalli,
Yeshvantpur, Whitefield, Kuppam, Bhairanayakanahalli, Rayakottai, Patchur,
Dodbele, Kelamangalam, Krishnadevaraya Halt, Hirehalli, Bisantham,
SomanayakanaPatti, Marandahalli, Gnananbharathi Halt, Nidvanda, Gudupalli,
MulanurKyatsandra&Carmelaram.
|
Bengaluru
|
35
Stations
Ramanagaram,
Nidaghatta Halt, Maddur, Mandya, Palahalli, Muttampatti, Sivadi,
Semmandapatti, Karuvalli, Muddalinganahalli, Dharmapuri, Royakottai,
Dobbespet, BEML Nagar, Oorgaum, Dodbele, Somanayakanapatti, Gudupalli,
Bisantam, Tyakal, Toppur, Perianagatunai, Nidvanda, Soledanahalli,
Naganhalli, Gnanabharathi, Kengeri, Hejjala, Ketohalli, Hebbal, Bangarapet,
Champion, Somnayakanpatti, Mulanur, Bisantam
|
|
Mysuru
|
13
Stations
Shivamogga
Town, Hassan, Birur, Ashokapuram, Subramanya Road, Bommagundanakere, Kumsi,
Bantawal, Akkhihebalu, Amritapura, Ramagiri, Holalkere&Kadkola
|
Mysuru
|
43
Stations
Tarikere,
Subramanya Road, Chamarajanagar, Chamrajpuram, Nanjangud Town, Chitradurga,
KrishnarajanagarHolenarasipura, Kabakaputtur, Mariyalgangavadihalt,
Badanaguppe, Konanur, Arjunahalli, Birahalli, Kavalande, Narasambudhi,
Chinnadagudihundi halt, Bageshpura, Akkhihebballu, Bantawal, Mandagere,
Mavinakere, Bantawal, Kumsi, Anandapuram, Habanghatta, Kalluryedahalli,
Dornahalli, Sravanur (halt), Sujatapuram(halt), Tandavapura Halt,
KrishnarajasagaraBommagundanakere, Molakalamuru, Kadkola, Belagula,
Sagarakatte, Hosaagrahara, Shivani, Holalkere, Amritapura, Thalaku,Sakleshpur
|
New ROBs/RUBs in
Karnataka
|
Sl. No
|
LC No.
|
Between Stations
|
Cost
(Rs.in Cr.)
|
|
1
|
380
|
Desuru-Belgavi(near
Belgavi)
|
33.48
|
|
2
|
386
|
Belagavi-Sambre(at
Belgavi)
|
22.70
|
|
3
|
305
|
Kyarrkop-Mugad
|
6.64
|
|
4
|
316
|
Kambarganavi-Kashanhatti
|
17.36
|
|
5
|
34
|
Badami-Guledagudda(at
Badami)
|
23.05
|
|
6
|
41
|
Guledagudda-Bagalkot(at
Guledagudda)
|
20.80
|
|
7
|
34
|
Bhadravati-Shivamogga
Town(near Bhadravati)
|
20.19
|
|
8
|
49
|
Shivamogga
Town-Kumsi(at Shivamogga Town)
|
22.95
|
|
9
|
52
|
Shivamogga
Town-Kumsi(near Shivamogga Town)
|
18.86
|
|
10
|
217
|
Chalgeri-Ranibennur
|
29.08
|
|
11
|
218
|
Ranibennur-Devargudda
|
31.89
|
|
12
|
219
|
Ranibennur-Devargudda
|
10.41
|
|
13
|
184
|
Mayakonda-Kodaganur
|
33.33
|
|
14
|
7
|
Mysuru-Belagola
|
07.95
|
|
15
|
1
|
Chikjajur-Amritapura
|
19.85
|
|
16
|
15
|
Amritapura-Chitradurga
|
28.51
|
|
17
|
22
|
Chitradurga-Balenahalli(at
Chitradurga)
|
34.93
|
|
18
|
112
|
Korvangala-Bagaeshpura
|
23.95
|
|
19
|
76
|
Mandya-Yeliyur
|
16.48
|
|
20
|
06
|
Yelahanka-Channasandra
|
16.22
|
|
21
|
132
|
Karmelaram-Baiyyapanahalli
|
41.11
|
|
22
|
133
|
Karmelaram-Baiyyapanahalli
|
42.93
|
|
Total
|
522.67
|
||
New RUBs/Subways
|
SN
|
LC No.
|
Between Station
|
KM/HP
|
Cost
(Rs.in Cr.)
|
|
1
|
56
|
Almatti-Wandal
|
131/300-400
|
6.28
|
|
2
|
61
|
Wandal-Basavanbagewadi Road
|
142/200-300
|
|
|
3
|
92
|
Minchinal-Nimbal
|
209/700-800
|
11.05
|
|
4
|
96
|
Minchinal-Nimbal
|
218/500-600
|
|
|
5
|
98
|
Minchinal-Nimbal
|
222/600-700
|
|
|
6
|
64
|
Shivamogga Town-Kumsi
|
77/100-200
|
5.70
|
|
7
|
130
|
Anandapuram-Sagar Jambagaru
|
143/600-700
|
|
|
8
|
85
|
Tiptur-Honnavalli Road
|
141/600-700
|
|
|
9
|
8
|
Ashokpuram-Kadakola
|
8/500-600
|
5.70
|
|
10
|
11
|
Ashokpuram-Kadakola
|
13/000-100
|
|
|
11
|
30
|
Nanjangud Town-Chamaraja Nagar
|
34/700-800
|
|
|
12
|
10
|
Belagula-Sagarkatte
|
14/500-600
|
9.50
|
|
13
|
49
|
Hosaagrahara-Akkihebbalu
|
55/100-200
|
|
|
14
|
62
|
Akkihebbalu-Mandagere
|
67/300-400
|
|
|
15
|
127
|
Habhanghatta-Arsikere
|
155/500-600
|
|
|
16
|
130
|
Habhanghatta-Arsikere
|
159/700-800
|
|
|
Grand Total
|
38.23
|
|||