Ahmedabad Metro Trial Runs Conducted on January 31,2019
Ahmedabad, Metro Rail News: Gujarat Metro Rail Corporation (GMRC) conducted the first trial run of the Ahmedabad metro rail was conducted on January 31, 2019, Which announced that its commercial operations will start from March this year.
The government plans to start from March operations of the metro rail on 6.5-km route, which is a part of the first phase from Vastral in the city to Apparel Park.
“The first test of the train was successfully carried out today on the test track of 900 meters at Apparel Park,” a statement by GMRC said.
“The first train-set of Ahmedabad Metro had arrived at Apparel Park Depot on January 1, 2019 and was undergoing technical examination, safety checks and tests required for the regular run of the train,” the statement said.