Traffic Block and Power Block on 07.03.2020 and 08.03.2020 -Eastern Railway

Traffic  Block and Power Block on 07.03.2020 and 08.03.2020 -Eastern Railway

TRAFFIC & POWER BLOCK FOR CONSTRUCTION OF LIMITED HEIGHT SUBWAY
Kolkata, March 5, 2020
For construction of Limited Height Sub-way (LHS), 9½ hrs. Traffic & Power Block from 22.35 hrs. to 08.05 hrs. in the night of 7/8-3-2020 (Saturday/Sunday) o­n Barasat – Bangaon Section will be imposed.
Consequently following arrangements have been made:
Cancellation of trains:
·33861/33860 Sealdah – Bangaon – Sealdah local will remain cancelled o­n Saturday (7/8-3-2020).
·33815 Sealdah-Bangaon Local, 33820 Bangaon – Sealdah Local and 33361 Barasat – Bangaon Local will remain cancelled o­n Sunday (8.3.2020).
Short Termination:
Besides, 3 (three) Sealdah- Bangaon locals (33857, 33859, 33863) will terminate at Habra o­n Saturday (7.3.2020) and 3 (three)  Sealdah- Bangaon locals (33811,33813,33817) will terminate at Habra & o­ne Bangaon- Majerhat local (30344) will originate from Barasat o­n Sunday (8.3.2020).
Inconvenience likely to be caused is deeply regretted